Pepsi Bottling Plant Rocking Slab Stabilization

Erosion beneath warehouse concrete slab floor causing uneven joints and rocking slabs at Pepsi Bottling Plant in Nashville, TN
About The Project
Contractor Mid-South Concrete Leveling (MSCL)
Project Location Nashville, TN
Product Used Terrathane™ 24-003

Problem

  • Erosion beneath warehouse concrete slab floor causing uneven joints and rocking slabs
  • Forklift traffic travelling over the unsupported slabs caused the slabs to rock up and down and created breaks and fractures called “joint spalling”
  • Rocking and unlevel slabs were causing jolts and bumps to forklifts, leading to falling loads and safety issues

Solution

  • Clean out all joints and remove the debris
  • Inject TerraThane™ 24-003 polyurethane on a 4 ft grid pattern to fill joints, voids and stabilize rocking slabs

Results

  • Stabilized over 130 ft of slabs
  • Work performed to minimize operational interruption
  • Fast cure time ensured the installation locations would be drive-able during the same day as the installation

Project Gallery

Other Case Studies

Rocking Slab Stabilization raising polyurethane foam Arizona

Ram Jack Arizona uses NCFI TerraThane 24-003 to Stabilize 47 Rocking Slabs

Ram Jack Arizona used NCFI TerraThane 24-003 to stabilize the joints of 47 slabs, completing the initial phase of the project in approximately 12 hours.

Read More →

Slab Fix, LLC Repairs Florida Seawall using NCFI Terra-Lok™ 24-120 Single Component System

Over time, the homeowner noticed signs of deterioration in their concrete seawall. Tidal fluctuation was causing soil erosion underneath and behind the seawall. Terra-Lok™ 24-120 polyurethane was used in the bulkhead repair.

Read More →